How far apart fence posts go
Fence guides space wood posts at most 8 ft apart so standard 8 ft rails reach from post to post; Simpson Strong-Tie's fence plan marks a post every 8 ft, and a Home Depot fence guide recommends 6 ft for the most strength. Panels set the spacing for you: the panel's width plus one post (Freedom), such as 96 in center to center for Barrette's 6 ft vinyl panels with 5 in posts.
Closer posts cost more posts. A straight 96 ft fence takes 13 posts at 8 ft and 17 posts at 6 ft. Hurricane areas can require much closer spacing: one Florida city's detail calls for posts 4 ft apart on a 6 ft fence. Check local rules.
How deep to set fence posts
Quikrete, Sakrete and Outdoor Essentials all put about a third of the post's full length in the ground: a 6 ft fence wants about 3 ft in the ground, on a post at least 9 ft long. Simpson's rule of thumb is shallower (2 ft for a 6 ft fence), and a Home Depot guide asks for at least 2 ft; in cold climates, go below the frost line. Outdoor Essentials sets end, corner and gate posts 6 in deeper, since they carry the most load.
| Fence height | Post in the ground | Hole depth with gravel | Post length |
|---|---|---|---|
| 3 ft | 1 ft 6 in | 2 ft | 4 ft 6 in |
| 4 ft | 2 ft | 2 ft 6 in | 6 ft |
| 5 ft | 2 ft 6 in | 3 ft | 7 ft 6 in |
| 6 ft | 3 ft | 3 ft 6 in | 9 ft |
| 8 ft | 4 ft | 4 ft 6 in | 12 ft |
How wide to dig, and the gravel
- Width: 3 times the post (Quikrete, Sakrete): 10.5 in for a 4 × 4, which is 3.5 in square. Fence guides say 10 to 12 in; vinyl fence makers use their own sizes, such as 8 in for a 4 × 4.
- Gravel: 6 in of gravel in the bottom of each hole, so water drains away from the end of the post (Quikrete; Sakrete says 4 to 6 in).
- Concrete: Quikrete pours fast-setting mix dry into the hole until it is 3 to 4 in from the top.
Concrete per post
The concrete fills the hole around the post, above the gravel. For a 4 × 4 in a 10.5 in hole with a third of a 6 ft fence's post in the ground, that is about 4.1 bags of 50 lb fast-setting mix (about 0.375 cu ft each, Quikrete) per post. Sakrete's table for a 10 in hole: 1¼ bags at 12 in deep, 2 at 18 in, 2½ at 24 in and 3 at 30 in. For footings and piers, see concrete for footings and steps or the concrete calculator.
Worked example
Backyard: 50, 100 and 46 ft sides plus a 4 ft gate
| Fence | 196 linear ft |
|---|---|
| Gate openings | 4 linear ft |
| Gates | 1 gate |
| Most space between posts | 8 ft |
| Sections | 26 sections |
| End, corner and gate posts | 5 posts |
| Line posts | 23 posts |
| Posts | 28 posts |
| Rails (3 per section) | 78 rails |
| Pickets, gates included | 439 pickets |
| Concrete per post (hole − post, from the gravel up to the ground) | 0.06 cu yd |
| Concrete, all posts | 1.61 cu yd |
| 50 lb fast-setting bags, rounded up | 116 bags |
| 80 lb bags, rounded up | 73 bags |
| Gravel, all holes | 0.31 cu yd |
| Post length, at least | 9 ft |
Answer: 28 posts. Every side and gate ends at a post, shared at corners, with line posts between sections.
Work out the posts for your fence
Common mistakes
- Counting posts as length ÷ spacing. Add one for the end, and one for each corner and gate.
- Setting every post the same depth. Outdoor Essentials sets end, corner and gate posts at least 6 in deeper than line posts.
- Skipping the gravel. Quikrete and Outdoor Essentials put gravel under each post so water drains away from its bottom.
- Digging before checking. Call 811 to mark buried utilities, and check the property line and local height limits.
Related tools and guides
- CalculatorFence CalculatorWork out the posts, rails and pickets or panels for a fence with gates, and the concrete for each post hole, from the length of each side of the fence.
- CalculatorConcrete CalculatorWork out the concrete for a slab, footings, post holes or steps: cubic yards with waste, the ready-mix order, and how many 40, 60 or 80 lb bags to buy.
- GuideHow Much Concrete for Footings, Post Holes and StepsHow to measure footings, post holes, tubes and steps for concrete, the code minimums for footings and stairs, and how many bags each one takes, step by step.